Energy Vampires: The AI Data Centres Draining Australia
Greenpeace Australia Pacific
ENRICHED
Details
- Date Published
- 27 May 2026
- Priority Score
- 3
- Australian
- Yes
- Created
- 27 May 2026, 08:00 am
Description
The frenzied rollout of AI data centres in Australia is rushing through massive new projects, which will derail Australia’s energy transition unless the government urgently intervenes.
Summary
This report examines the rapid expansion of AI data centers in Australia and their significant impact on the country's energy transition and climate goals. It highlights how the immense power demands of frontier AI models are driving a potential gas-fired energy boom, specifically referencing large-scale projects like the Mamre Road Data Centre Campus. The findings suggest that current AI infrastructure deployment lacks transparency regarding the purposes of computation, including potential use in warfare and human rights violations. The authors advocate for an urgent moratorium on new developments until legislated safety and sustainability guardrails are established to mitigate national-level environmental and societal risks.
Body
Greenpeace campaigner Solaye Snider at the site of the proposed Mamre Rd data centre in Sydney. If approved, the data centre will be the biggest in Australia and will generate peak annual grid emissions equivalent to that produced by 560,000 petrol cars. © Toby Davidson / Greenpeace
A new report from Greenpeace Australia Pacific and independent expert Ketan Joshi reveals how the frenzied rollout of AI data centres in Australia is set to derail the renewable energy transition, entrench gas and turbocharge climate pollution, prompting calls for an urgent moratorium on data centre approvals until appropriate guardrails are in place.
The frenzied rollout of AI data centres in Australia is rushing through massive new projects, which will derail Australia’s energy transition unless the government urgently intervenes.
View full report
View this post on Instagram A post shared by Greenpeace Australia Pacific (@greenpeaceap)
Key findings
The frenzied rollout of AI data centres in Australia is rushing through massive new projects, which will derail Australia’s energy transition unless the government urgently intervenes. Our conservative assumptions mean this impact is understated, in this analysis.
Australia’s biggest proposed data centre, the 1GW Mamre Road Data Centre Campus in Western Sydney, will generate peak annual grid emissions equivalent to that produced by 560,000 petrol cars for a year or all domestic flights within NSW in 2023.
Data centres already fail to cover their own emissions with new renewables and their rollout will dramatically hold back Australia’s energy transition.
No data centre operator analysed in this report adequately proves their claim of driving Australia’s renewable energy growth. Claims they are doing this through truly “additional” new power purchasing agreements for renewable energy are unsubstantiated.
There are early signs of a data centre-fuelled gas boom in Australia, which will come with massive, nationally significant climate costs. For example, the Tamboran proposal for the Northern Territory would effectively double the state’s emissions. In NSW, Cloud Carrier’s proposed gas-fired project would wipe out NSW’s entire projected 2028 emissions cuts.
The Big Horn Data Hub and the Hardin Generating Station in Hardin, Montana. © Janie Osborne / Greenpeace
Even if only 1 in 4 new Australian data centres were powered by new on-site gas, it would result in 2.8x higher total emissions compared to using grid power.
New analysis shows that on-site gas for data centres globally could fuel emissions that exceed Brazil’s total power grid emissions by 2030.
Fossil fuel corporations are quietly joining the data centre lobby group as members, and sponsoring and attending technology industry conferences. The two industries are reinforcing each other’s talking points and PR spin.
Clean Our Cloud Action in Seattle. © Greenpeace
Data centre operators do not disclose the customers of an individual facility, the purpose of the computations performed there, or site-specific energy consumption, despite the industry’s defense of its ‘critical infrastructure’ status or claims of transparency. It is a matter of public record that AI is being used for abuse, war and other human rights violations.
Data centres can be ‘right sized’ through community ownership schemes, well-deployed AI software and strict moratoria to allow for democratic governance of this industry.
An aerial view of the Facebook Data Center in Forest City. The 150-acre facility is the second Facebook-built data center in the United States. © Greenpeace
This report recommends:
An urgent moratorium on data centre development until safeguards are legislated
Binding, legislated standards for AI development, including substantiated claims of additional renewable energy
Full disclosure of services delivered, emissions, finances and energy use, per project
Full assessment of compliance with human rights frameworks
View full report
Lead author: Ketan Joshi is an independent climate, environment and sustainability expert. He was the lead author on “The AI Climate Hoax”, published with several corporate accountability and environmental groups in 2026, and previously wrote “Windfall: Unlocking a Fossil Free Future” with the University of New South Wales Press. He worked for eight years in Australia’s renewable energy sector (corporate and government), and has worked with European NGOs working on climate communications and corporate accountability.